When corroded piping and pipe support that are part of a processing plant’s vapor recovery system necessitated swift and precise action, Suncor Energy turned to Tetra Tech’s experts.

The project called for the replacement of the piping and structural supports on an extremely tight schedule. We completed the first design phase in one week to allow for rapid construction with project completion in three weeks.

Tetra Tech’s responsiveness and performance ultimately garnered a nomination for Suncor’s President’s Operational Excellence Award in the Environmental and Sustainability category. Nominations for the Operational Excellence category are recognized for their contribution to significantly improve Suncor’s environmental performance and go beyond compliance in key areas. They demonstrate Suncor’s commitment to the triple bottom line of environment, economic, and social benefits.